1953 - Maximum Number of Weeks for Which You Can Work\.
Medium
There are `n` projects numbered from `0` to `n - 1`. You are given an integer array `milestones` where each `milestones[i]` denotes the number of milestones the
ith project has.
You can work on the projects following these two rules:
* Every week, you will finish **exactly one** milestone of **one** project. You **must** work every week.
* You **cannot** work on two milestones from the same project for two **consecutive** weeks.
Once all the milestones of all the projects are finished, or if the only milestones that you can work on will cause you to violate the above rules, you will **stop working**. Note that you may not be able to finish every project's milestones due to these constraints.
Return _the **maximum** number of weeks you would be able to work on the projects without violating the rules mentioned above_.
**Example 1:**
**Input:** milestones = [1,2,3]
**Output:** 6
**Explanation:** One possible scenario is:
- During the 1st week, you will work on a milestone of project 0.
- During the 2nd week, you will work on a milestone of project 2.
- During the 3rd week, you will work on a milestone of project 1.
- During the 4th week, you will work on a milestone of project 2.
- During the 5th week, you will work on a milestone of project 1.
- During the 6th week, you will work on a milestone of project 2.
The total number of weeks is 6.
**Example 2:**
**Input:** milestones = [5,2,1]
**Output:** 7
**Explanation:** One possible scenario is:
- During the 1st week, you will work on a milestone of project 0.
- During the 2nd week, you will work on a milestone of project 1.
- During the 3rd week, you will work on a milestone of project 0.
- During the 4th week, you will work on a milestone of project 1.
- During the 5th week, you will work on a milestone of project 0.
- During the 6th week, you will work on a milestone of project 2.
- During the 7th week, you will work on a milestone of project 0.
The total number of weeks is 7. Note that you cannot work on the last milestone of project 0 on 8th week because it would violate the rules. Thus, one milestone in project 0 will remain unfinished.
**Constraints:**
* `n == milestones.length`
* 1 <= n <= 105
* 1 <= milestones[i] <= 109-
Constructor Summary
Constructors -
Method Summary
-
Constructor Details
-
Solution
public Solution()
-
-
Method Details
-
numberOfWeeks
public long numberOfWeeks(int[] milestones)
-