How to Calculate Liquidated Damages in Construction

This title was summarized by AI from the post below.

How to Calculate Liquidated Damages (LD) in Construction Projects Liquidated Damages (LD) are pre-agreed amounts payable by the Contractor for delays in project completion. Here’s how to calculate them step by step: Check the LD Clause Example: “1% of the Contract Price per week of delay, capped at 10%.” Confirm the Contract Price Contract Value = USD 50,000,000 Determine Revised Completion Date: Include approved Extensions of Time (EOT). Revised Completion = 30 June 2025 Identify Actual Completion Date Actual Completion = 10 August 2025 Calculate Delay Duration (Delay = Actual – Revised) 10 Aug – 30 Jun = 6 weeks delay Apply the LD Formula (LD = (Delay Weeks × % per Week × Contract Value LD = 6 × 1% × 50,000,000 = USD 3,000,000 Check the Maximum Cap Cap = 10% × 50,000,000 = USD 5,000,000 Since 3,000,000 < 5,000,000 → Full amount is payable

In addition to the above insightful information, it is also important to check if there is any revised Contract Price due to approved or executed Variation Orders, as the LD amount should be calculated based on the updated Contract Price.

If the total amount exceeds the maximum cap, the contractor should receive the full payment of 5,000,000 USD. After this payment is made, the contractor may delay their work for an extended period without receiving any further payments. I would like to know if this is correct or not.

Like
Reply

0.1% per day and also total LD amount not greater than 10% of the contract amount.

Like
Reply

Asif Mehmood Kindly explain, What if LD value exceeds maximum Cap, and how it should be caluculated.

Like
Reply

In Pakistan it is applied in the same manner and is termed as penalty on delay in KPPRA rules.

Like
Reply
See more comments

To view or add a comment, sign in

Explore content categories